Wednesday, January 30, 2008

TransCo finishes repairs on damaged towers

The National Transmission Corporation (TransCo) said it has completed repairs on eight of the nine transmission line towers that were damaged by the recent series of bombings in the Lanao provinces.

TransCo assistant vice president for Mindanao OIC Emmanuel Abellanosa said TransCo’s line crews have already repaired Towers 22, 26, 4, 36, 19, 15, 8 and 9.

“We are now rushing repairs on the ninth, Tower 50, in Lanao del Sur,” he said.

Abellanosa also reiterated that contingency measures to address the situation are firmly in place.

“Although the bombings have affected the efficiency and reliability of our system, we are in control of the situation. If these destructive acts continue, we have a system in place to mitigate a possible prolonged power interruption,” he added.

Abellanosa cited TransCo’s linemen for risking their lives in order to repair the transmission towers and energize the lines at the soonest possible time.

He also thanked the Philippine National Police and Philippine Army contingents assigned in the Lanao areas for their help. “We are constantly in coordination with them in these trying times,” he said. (transco pr)

Tuesday, January 29, 2008

TransCo Adopts Contingency Measures on felled towers

The National Transmission Corporation (TransCo) has activated a number of contingency measures today, January 25, to normalize power supply in the grid following the reduction of its power transmission capacity to various parts of Mindanao due to three separate bombings of its transmission line towers early morning today.

TransCo line crews have been dispatched to the trouble spots to immediately start repairs on Tower 8 and 9 of the Abaga-Tagoloan line in Balo-i, Lanao del Sur and Tower 50 of the Agus 2-Kibawe line in Brgy. Fatima, Iligan City respectively.

TransCo OIC-Assistant VP Emmanuel Abellanosa said TransCo is dealing with the reduced transmission capacity in accordance with its contingency plan. The recent series of bombings have affected the efficient delivery of electricity to several provinces in Mindanao.

“All remedial measures are being done to restore the affected lines at the earliest time possible,” Abellanosa said.